September → November 2022

Construction New Accessible Amenities

Construction of new amenities building, accessible parking and connecting accessible pathway from car park to amenities.

July → August 2022

Construction of new Playground

Construction of playground elements of Stage One of the Masterplan Revitalisation. Initial works include new playground and pathways, shelter and seating.

October 2021 → January 2022

Preparation for Construction - Revitalisation Mullaway Beach Reserve: Stage One

Environmental assessment, detailed design, procurement, site preparation.

March → September 2021

Assessment of Feedback from Community - Revitalisation Mullaway Beach Reserve

Community input during the public consultation period is assessed by the Project Team as part of the design review process, and where appropriate, design changes may be recommended. 

29 January → 01 March 2021

Revitalisation Mullaway Beach Reserve - Community Comments invited on Concept Plans

The draft masterplan for the upgrades of Mullaway Beach Reserve is on public exhibition from Friday January 29 through to 5pm Monday March 1, 2021.