20 March → 30 September 2018

Construction

1st stages include new drainage, relocation of water main and 10 power poles. Roadworks start in April, along with parking bays and kerb and gutter, to be followed by shared pathways, driveway replacement then landscaping

September 2017 → January 2018

Detailed design and planning

Detailed design and planning informed by consultations regarding landscaping and bus stop location, heritage and cultural studies.
07 August → 21 August 2017

Consultation with Sandy Beach residents to select preferred concept design option.

Online survey, direct communications with SANDBAG and individual residents, consideration of written submissions.