07 December → 11 December 2020

Beach Street Entrance and pathway works timeframe - Traffic Control applies during works

Works expected to take up to two days during this timeframe. Thank you for your patience as we near opening date.

December 2020

Open new playground and amenities to the community.

November → December 2020

Playground and pathways construction and landscaping

October → November 2020

Construction of new amenities building.

October 2020

Formwork and slab construction for new amenities building.

12 October 2020

Extension to seven days per week construction works

Contractors will be working on site seven days each week, from October 12 (following NSW school holidays).

26 October → 11 December 2020

Playground construction, furniture, shade and landscaping

12 October → 26 October 2020

New amenities assembled on site at the Reserve

August → October 2020

New amenities pre-cast offsite.

18 August 2020

Closure of Reserve car park at playground and amenities

The car park at the amenities and playground is to be closed permanently from August 18, in line with the concept design for the Woolgoolga Beach Reserve and Woolgoolga Foreshores, detauiled in the Woolgoolga Town Centre Masterplan, adopted 2018.

15 July 2020

Burnett Civil Contractors start civil works to prepare the site.

May 2020

Site Fencing Erected

December 2019

Site Preparation Preliminary Works

22 December 2020

PLAYGROUND OPENS TO THE PUBLIC

09 March → 31 March 2021

Completion of New Amenities

Final works to complete the new amenities building. Weather-permitting, it is hoped to open the new facilities for the East long weekend.

03 May → 31 May 2021

Removal of old playground and amenities

The old playground and amenities will be decommissioned and landscaping works will begin to restore the sites.