Beach Street Entrance and pathway works timeframe - Traffic Control applies during works
Works expected to take up to two days during this timeframe. Thank you for your patience as we near opening date.
December 2020
Open new playground and amenities to the community.
November → December 2020
Playground and pathways construction and landscaping
October → November 2020
Construction of new amenities building.
October 2020
Formwork and slab construction for new amenities building.
12 October 2020
Extension to seven days per week construction works
Contractors will be working on site seven days each week, from October 12 (following NSW school holidays).
26 October → 11 December 2020
Playground construction, furniture, shade and landscaping
12 October → 26 October 2020
New amenities assembled on site at the Reserve
August → October 2020
New amenities pre-cast offsite.
18 August 2020
Closure of Reserve car park at playground and amenities
The car park at the amenities and playground is to be closed permanently from August 18, in line with the concept design for the Woolgoolga Beach Reserve and Woolgoolga Foreshores, detauiled in the Woolgoolga Town Centre Masterplan, adopted 2018.
15 July 2020
Burnett Civil Contractors start civil works to prepare the site.
May 2020
Site Fencing Erected
December 2019
Site Preparation Preliminary Works
22 December 2020
PLAYGROUND OPENS TO THE PUBLIC
09 March → 31 March 2021
Completion of New Amenities
Final works to complete the new amenities building. Weather-permitting, it is hoped to open the new facilities for the East long weekend.
03 May → 31 May 2021
Removal of old playground and amenities
The old playground and amenities will be decommissioned and landscaping works will begin to restore the sites.