Draft Developer Contributions Plan: Hearnes Lake/Sandy Beach

Share Draft Developer Contributions Plan: Hearnes Lake/Sandy Beach on Facebook Share Draft Developer Contributions Plan: Hearnes Lake/Sandy Beach on Twitter Share Draft Developer Contributions Plan: Hearnes Lake/Sandy Beach on Linkedin Email Draft Developer Contributions Plan: Hearnes Lake/Sandy Beach link

Consultation has concluded

The public display period for this exhibition is now CLOSED. The revised Developer Contributons Plan was adopted by Council on the 10 May 2018 with the Developer Contributions Plans becoming effective on the 23 May 2018. Further information regarding this previous exhibition is contained in this engagement.

DRAFT REVIEW 2018 TO DEVELOPER CONTRIBUTIONS PLAN FOR HEARNES LAKE/SANDY BEACH

On 22 March 2018 Council resolved to place the following draft item on public exhibition for a period of 28 days:

  • Draft Developer Contributions Plan 2018 - Hearnes Lake/Sandy Beach

A review has been conducted on the Hearnes Lake / Sandy Beach

The public display period for this exhibition is now CLOSED. The revised Developer Contributons Plan was adopted by Council on the 10 May 2018 with the Developer Contributions Plans becoming effective on the 23 May 2018. Further information regarding this previous exhibition is contained in this engagement.

DRAFT REVIEW 2018 TO DEVELOPER CONTRIBUTIONS PLAN FOR HEARNES LAKE/SANDY BEACH

On 22 March 2018 Council resolved to place the following draft item on public exhibition for a period of 28 days:

  • Draft Developer Contributions Plan 2018 - Hearnes Lake/Sandy Beach

A review has been conducted on the Hearnes Lake / Sandy Beach Release Area Developer Contributions Plan. This plan has been reviewed to ensure financial viability and reasonable facilities are provided to the local community members in this release area.

The review has resulted in:

  • A proposed reduction in contributions of $2,574.44 per lot from $35,313.70 to $32,739.27 per lot in the Western Precinct.

  • A proposed increase in contributions of $3,847.67 per lot from $33,949.61 to $37,797.28 per lot in the Northern Precinct.

  • A proposed reduction in contributions of $2,785.12 per lot from $29,818.71 to $27,033.59 in the Eastern Precinct.

This provides a cumulative reduction of $1,511.89 across all precincts in the catchment. All figures are inclusive of water and wastewater contributions.

Development has progressed in accordance with this plan; that is, specific works have been completed within the existing schedule of works. Therefore, it is necessary for the plan to be reviewed and amended to ensure financial viability and to also ensure it meets the future development needs of the urban release area.

  • CLOSED: This survey has concluded.

    In order for Council to consider electronic submissions each submission must:
    a) contain legitimate contact details;
    b) be received by Council during the submission period; and
    c) be correctly or ‘properly’ made to include the proposal title and reasons for the submission.

    Submissions which do not satisfy the above criteria may not be considered. Further details can be found in Council's Submission Policy.

    Council is committed to openness and transparency in its decision making processes.  The Government Information (Public Access) Act 2009 requires Council to provide public access to information held unless there are overriding public interest considerations against disclosure.  Any submissions received will be made publicly available unless the writer can demonstrate that the release of part or all of the information would not be in the public interest.  However, Council would be obliged to release information as required by court order or other specific law.

    Consultation has concluded
    Share Electronic Submissions on Facebook Share Electronic Submissions on Twitter Share Electronic Submissions on Linkedin Email Electronic Submissions link