In partnership with NSW Government and the Regional Sports Infrastructure Fund, Coffs Harbour City Council in June 2022 completed Stage 2 of The Coffs Coast Regional Sports Hub Project. The entire project was delivered in four stages;
- Stage 1 - The upgrade to the C.ex Coffs International Stadium – “Building an EPIC Stadium for the Future” – Completed
- Stage 2 - Three new rectangular fields (2 synthetic, 1 turf) and associated amenities – Project under construction
- Stage 3 - Regional Indoor Sports Centre – Future Project
- Stage 4 – Field construction on NW corner of playing fields precinct – FutureContinue reading
In partnership with NSW Government and the Regional Sports Infrastructure Fund, Coffs Harbour City Council in June 2022 completed Stage 2 of The Coffs Coast Regional Sports Hub Project. The entire project was delivered in four stages;
- Stage 1 - The upgrade to the C.ex Coffs International Stadium – “Building an EPIC Stadium for the Future” – Completed
- Stage 2 - Three new rectangular fields (2 synthetic, 1 turf) and associated amenities – Project under construction
- Stage 3 - Regional Indoor Sports Centre – Future Project
- Stage 4 – Field construction on NW corner of playing fields precinct – Future Project
Stage 2 provided an increase in provision of sporting assets benefits multiple sports from local through to regional, state, national and international levels, as well as improving vital connections throughout the precinct to neighbouring partners. Stage 2 will deliver:
Three new rectangular fields 2 synthetic and 1 turf, with Australian Standard lighting. The turf field will have sub surface drainage and irrigation
New amenity block including inclusive change rooms and officiating rooms, canteen, bar and storage rooms to service the new fields
Extension to the amenity block between Field 1 and 2 at CCSLP. To include two new regional standard inclusive change rooms, officials rooms, storage room and canteen
Car park and access road for the new fields and much needed major event parking
Linkages and connectivity throughout the precinct which incorporates new shared paths for pedestrian and cycle traffic around the facility and between the precinct and the education and health campuses
Business case and further studies for a proposed regional indoor sports facility, (stage 3) within the Coffs Coast Regional Sports Hub footprint
provide new and upgraded facilities to further provide for inclusive needs of athletes and spectators who compete in the region, along with connectivity throughout the entire precinct, linking the neighbouring health and education campuses with the sporting precinct which adds to the overall provision for the sporting community.
The Coffs Coast Regional Sports Hub maximises the potential of the CCSLP as a multi-sport facility and provides significant alignment and opportunity for ongoing partnership with neighbouring assets such as Southern Cross University and Coffs Harbour Health Campus.
Lifecycle
-
2017-2019: Regional Sports Hub Stage 1 EPIC Upgrade
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageBuilding an EPIC Stadium for the Future, Upgrade of C.ex Coffs International Stadium.
-
April 2018: Regional Sports Hub Stage 2 Resolved @ Council Meeting
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageCoffs Harbour City Council resolved at its April 26 2018 meeting to submit an Expression of Interest (EOI) to the NSW Government’s Regional Sports Infrastructure Fund (RSIF) for the Coffs Coast Regional Sports Hub – Stage 2, to apply for $10,000,000 with Council contributing $2.500,000.
-
May 2018: EOI Submitted
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageExpression of Interest (EOI) submitted to the NSW Government’s Regional Sports Infrastructure Fund (RSIF) for the Coffs Coast Regional Sports Hub – Stage 2.
-
August 2018: Application Submitted
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageBusiness Case and application submitted to the NSW Government’s Regional Sports Infrastructure Fund (RSIF) for the Coffs Coast Regional Sports Hub – Stage 2.
-
October 2018: Application Successful
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageCoffs Harbour City Council secures $10,000,000 in grant funding.
-
December 2018: Agreement Executed
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageDeed of Agreement with NSW Government’s Regional Sports Infrastructure Fund (RSIF) executed for the Coffs Coast Regional Sports Hub – Stage 2.
-
January – March 2019: Project Commences
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageProject Charter created and Project Steering Committee established
-
March 2019: Regional Indoor Sports Facility Business Case commenced
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageBusiness case and further studies for a proposed regional indoor sports facility, (stage 3) within the Coffs Coast Regional Sports Hub footprint commenced.
-
June 2019: Pedestrian connectivity commenced
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageWorks begin on the linkages and connectivity throughout the precinct which incorporates new shared paths for pedestrian and cycle traffic around the facility and between the Coffs Coast Sport & Leisure Precinct and the Coffs Harbour Education Campus and the Coffs Harbour Education Campus Health Campuses.
-
March 2020: Pedestrian Connectivity COMPLETED
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageWorks completed on the linkages and connectivity throughout the precinct which incorporates new shared paths for pedestrian and cycle traffic around the facility and between the Coffs Coast Sport & Leisure Precinct and the Coffs Harbour Education Campus and the Coffs Harbour Education Campus Health Campuses.
-
May 2020: Turf Field Commenced
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageConstruction of new rectangular turf field including subsurface drainage & irrigation commenced.
-
June 2020: Extension to Change Rooms Commenced
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageWorks begin on additional facilities to increase provision of the existing amenities to include new regional standard inclusive change and officiating rooms, storage areas and canteen between Coffs Coast Sport & Leisure Park 1 & 2.
-
September 2020: Anticipated commencement of 2 Synthetic Football fields
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageTwo synthetic football fields with FIFA Quality certification and multi-sport compliance.
Australian Standard lighting to 200 lux to all three fields.
-
October 2020: Anticipated commencement of new change rooms
The Coffs Coast Regional Sports Hub: Stage 2 has finished this stageNew amenity block including inclusive change rooms and officiating rooms, canteen and storage rooms to service the new fields.
-
January 2021: Anticipated commencement of The Hub2, internal roads and carparks
The Coffs Coast Regional Sports Hub: Stage 2 is currently at this stage -
April 2022: Project COMPLETE